Installation

Floor surface inspection

  • 1) Before lnstallation, it is required to be smooth without unevenness and bending of the existing floor surface. Mortar strength should be strong enough for the entire surface adhesion.
  • 2) Fill the cracks in the floor and remove all the substances such as oil and wax in advent defects after installation.
  • 3) Check if the surface strength of the floor is sufficient.
  • 4) In case of reconsted floor, overlapping instaion is prohibited. (Remove existing floor at first)
  • 5) Check the dryeness of the floor and ensure the drying time in case of moisture remaining. (Check humidity delow 5%) For a new building, allow sufficient curing period to reduce humidity to below 5% before installation.